Deck roofs with induction welding

Fastening the synthetic membrane (TPO or PVC) without penetrating it: induction plates fix the insulation to the deck and are then welded to the underside of the membrane with the induction machine. Suitable for steel, timber or concrete decks.

Where it is used. Flat roofs with TPO or PVC membranes on steel, timber or concrete decks, where an unpenetrated membrane, an optimised fastener layout or fewer fasteners overall is wanted.

3D illustration: Deck roofs with induction welding

How to install

  1. Lay the vapour barrier and place the insulation boards staggered.
  2. Choose the screw for the deck: EDS-B 5.8 or EFXHD for steel deck, EDS-H or EDS-B for timber, and GBS or EFHD for concrete.
  3. Fix the Ø80 induction plates (coated for TPO or PVC) on the insulation in a grid, denser in corner and perimeter zones according to the wind uplift calculation. The same fasteners hold the insulation. With thick or walkable insulation, use the plate with an EFT sleeve.
  4. Lay the membrane over the insulation and plates, without penetrating it, and weld the laps.
  5. Pass the induction machine over each plate: it detects the plate, heats it and activates the adhesive, which bonds to the underside of the membrane.
  6. Immediately place a magnet on each welded point to cool it and press the membrane while it sets. With EPS or XPS, use FYT PAD to protect the insulation from the heat.